As you would expect, we have had a lot going on this first week of the course closure. Our major cultural practices are going well and on schedule, and the tee leveling/regrassing and bridge work have started as planned. I had a lot of pictures and videos from the first two days of the closure so I consolidated them into a short movie linked below.
The video includes clips of some of the activities over the last 2 days:
Cultural Practices
- Terra Rake WTW for thatch removal
- Double Backtrack Verticut Greens
- Blow off Greens
- Mow Greens
- 5/8” Core Greens Aerification
- Core Removal
- Blow off remaining core debris
- Granular Fertilizer Greens (2x)
- Water in Fertilizer
- Topdress Greens
Tee Laser Leveling/Regrassing Project
- Sod Cutting Tee Areas
- Removal of Sod
Bridge Redecking
More updates as we move along this summer.